central iowa | kramer10 - 11/21/2021 06:42
So we are plowing in some tile to split the existing laterals that we on 50ft centers. We did not instal them. We are plowing in the new ones. Is there a way or what is the best way that I can map out the existing laterals and main. Is there a way I can map them with the plow so everything can be on the same map or is there a better way to do this. I would also like to label them like you do when you install them if it’s possible. Thanks
If you are only after where they are and not their depth you could survey them, then change the parameters of the install to only let the plow in the ground a little bit and do a “fake” install.
|