central - east central Minnesota - | rupert - 6/24/2012 12:25 Doing a bin foundation and wanting to pour the footer first and come back and do the floor. I was planning on leaving rebar exposed above the footer that would tie into the floor. Is that all i would need to do to tie it all together? Never done multiple pours before. thanks They make a product to "bind" the two pours together - ask your concrete supplier for it. And the additional rebar. It's not as critical with "green" concrete, but I'd still consider the concrete binder between pours. |