 central - east central Minnesota - | mnfarmboy - 9/14/2021 11:50 Anyone have an idea what is going price of clay taken out of field for road project? They say black dirt be put back on. .50-$1/yd. Sound right? Down here, close to Sherco Electric generating plant and a large construction solid waste land fill, within 20 miles - $1.50-$1.75 yard (this is pond liner clay). For road building barrow, at least $1 - $1.50 yrd. They get $1.25 - $1.65 yrd out of the bank for gravel mining. If screening rock out, then $3 - $5 yard for the rock. ETA: Who's the Contractor ? I'd want a bond for enough to cover reclamation cost, if they don't follow through. Talk with the road authority of the road project to get their take on reclamation cost.
Edited by iseedit 9/14/2021 16:46
|