scmn | Guy I worked for in college would line them up starting on Monday with finishing touches on Saturday with a 4 man crew. Figured layout, drill holes, concrete in holes first day, set poles, rafters, purlins second day, roof tin and trim sidewalls third day, build sliding doors and tin side walls fourth and fifth days, rake and corner along the way. 40x80x14' could finish in 4 days, 60x100x18' finish in 6 days. Did an 80x156x19 that took 2 weeks. We would start at 7 am and quit at 3:30 pm (7.5 hr days), boss also farmed and milked at 5 and 5.