North Central Kansas | So you are telling me in 5 years, that the price has gone up that much?
His 60x40x14 with cement pad, electrical, dirt work, turn key operation was $43,000!
dirt work $5000
electrical $5000
cement $13,000
turn key $3000
bldg $17,000
40x60x14 = 33,600/12=2800feet squared
$17,000/2800=$6.07
$6.07x25% (mark up) =1.5175+6.07=7.5878
66x16x40 = 42240 / 12 = 3520 feet squares
3520 * $7.5875 = $26,708
So where does the other $18,000 come into play?
did yours say without cement...mine does not clearly say that...just says budget........ | |
|