| Putting out a warning to avoid Midwest Electric and service out of Downs, IL. I hired them to power my grain storage facility October of 2023, the physical structure was complete and ready for wiring in September of 24. It was only partially completed for harvest with the expectation it would be finished soon after. Writing this warning November of 2025 with a still only partially functioning grain facility. I paid for an automated PLC run site and I have nothing more than an overpriced, over engineered analog system that again is only partially functional. | |
|