Osage iowa | I appreciate that you’re asking questions about the pad, but this needed to be addressed before the pour. I haven’t heard any decent replies just farmers that watch concrete getting poured. I dump 3,000 yds a year, I’ve never done it this way but I’ve seen it many times. It should work, I would’ve put 1/2in bar on 2ft squares and poured 6 to 8in thick in the middle. I would also undermine the center pour a few inches to make a ledge locking the two pours together. They probly used structural fiber which is some heavy duty stuff but it costs to much not to just use 1/2in bars. | |
|