Northeast Nebraska and Candelaria Philippines | dittfarms - 2/15/2021 18:03
How much was the 10kw upfront costs
Rough numbers today,
30 panels @ 200 = $6000
mounting hardware 30 @ 30 = $900
inverter $5000
labor $5000
wire, ect $2500
So about $20,000
Get a 20 kwh battery for around $8,000 to $10,000
check out www.midwestess.com in a month or so. Just getting up and running.
ess= energy storage systems