CMN | To remove cab I made 2 brackets from 1/2” iron that bolt where mirrors do, remove roof top then ran a pipe from one side to the other then rear of cab slide a chain down the cab post and hooked on the bottom on both rear corners, then came under with forklift fairly simple,just unbolted ECM’ and other electric box’s from rear of cab and layed them over the rear hitch unbolted steering valve from front sector that took care of steering lines then brake lines your AC heater hose steps and few other things, once cab is off you have so much room to work on it, I can’t see how it could take 70-80 hrs that rediculous I mean for almost 2 weeks straight of 8 hr days??????? I did a 275 last spring first time it was my own so didn’t keep track of time but I would say 40-45hrs tops