Dad is/was an Electrician - and says try this There must be moister down there somewhere
Dig a post hole using a Tractor Auger Digger down past the hard pan Now drive 10' of 3/4" gal pipe in leaving 4" out of ground (protect the Threads by putting a coupling on the drive end) Then test for ground - if good ground - Ok If no good ground add 5' more of pipe = 10'+5'+5'+++ Ground rods should be at least 10' apart Just an idea! There is also a "UFER Ground" = #8 or larger BARE Copper wire in a deep ditch 20' or better long _ Use connectors for dis-simmler metals |