SCIA | The last one we put up was right a a buck a bushel, complete. We did the concrete and wiring. Had a crew from SD do the erection. Has full floor, 20 HP 3phase fan, 10" unload, power sweep, several intermediate wells, out side stairs, ladder inside, 10k per hour spreader and a small heater to do quicker air dry. 70k storage, $69770. Put up in ' 12, so stuff has went up since then. Bought from a dealer that gives good early order, early pay discounts. | |
|